Industrial Engineering & Production Management

Productivity and Work Measurement

Principles and applications of productivity and work measurement for Mechanical Engineering and GATE & IES preparation.

Preparation Mode
119 Active Questions
Answers & Explanations Included
📖 Study the questions before taking the quiz examination. No timer • No attempt recorded • No marks awarded
Question 1 of 119
Original Exam: GATE (2015)
Productivity is defined as:
✓ Correct Answer: A
Explanation:
Productivity = Output / Input. It measures the efficiency of production, i.e., how much output is obtained per unit of input. Higher productivity means more output for the same input or same output with less input. For example, if a worker produces 50 units in 8 hours, productivity = 50/8 = 6.25 units/hour.
Difficulty: basic Type: conceptual
Question 2 of 119
Original Exam: IES (2018)
Which of the following is a measure of partial productivity?
✓ Correct Answer: B
Explanation:
Partial productivity measures the ratio of output to a single input factor. Labour productivity = Total output / Labour input is the most common partial productivity measure. Other partial productivity measures include Capital productivity = Output / Capital input and Material productivity = Output / Material input. Total factor productivity (TFP) considers all inputs simultaneously.
Difficulty: basic Type: conceptual
Question 3 of 119
Original Exam: GATE (2019)
A factory produces 500 units per day with 25 workers. If workers are reduced to 20 and output remains 500 units, the percentage increase in labour productivity is:
✓ Correct Answer: C
Explanation:
Initial labour productivity = 500/25 = 20 units/worker/day. New labour productivity = 500/20 = 25 units/worker/day. Percentage increase = (25-20)/20 x 100 = 25%. The same output is now produced with fewer workers.
Difficulty: basic Type: numerical
Question 4 of 119
Original Exam: IES (2016)
The ratio of standard hours produced to actual hours worked is called:
✓ Correct Answer: D
Explanation:
Efficiency = (Standard hours produced / Actual hours worked) x 100%. It measures how well actual performance compares to the standard. Efficiency > 100% means the worker performs better than standard. Utilization = Actual hours worked / Available hours. Performance rating is used during time study to adjust observed time to normal time.
Difficulty: basic Type: conceptual
Question 5 of 119
Original Exam: GATE (2017)
If a worker completes a job in 40 minutes that has a standard time of 50 minutes, the worker's efficiency is:
✓ Correct Answer: A
Explanation:
Efficiency = (Standard time / Actual time) x 100% = (50/40) x 100% = 125%. The worker completed the job faster than standard time, so efficiency exceeds 100%. Standard hours produced = 50 min. Actual hours worked = 40 min. Efficiency = 50/40 x 100% = 125%.
Difficulty: basic Type: numerical
Question 6 of 119
Original Exam: IES (2020)
Multi-factor productivity is calculated as:
✓ Correct Answer: B
Explanation:
Multi-factor productivity (MFP) or Total Factor Productivity (TFP) considers multiple inputs: MFP = Output / (Labour + Capital + Materials + Energy + Other inputs). All inputs are typically converted to monetary values. This gives a more comprehensive measure than partial productivity measures.
Difficulty: basic Type: conceptual
Question 7 of 119
Original Exam: GATE (2018)
A company's output increased from 1000 to 1200 units while inputs increased from Rs. 50,000 to Rs. 55,000. The productivity index is:
✓ Correct Answer: C
Explanation:
Old Productivity = 1000/50000 = 0.02 units/Rs. New Productivity = 1200/55000 = 0.02182 units/Rs. Productivity Index = 0.02182/0.02 = 1.091 approximately 1.09. Output increased by 20% but inputs increased by 10%, so net productivity gain is approximately 9%.
Difficulty: intermediate Type: numerical
Question 8 of 119
Original Exam: GATE (2014)
Work study is a combination of:
✓ Correct Answer: D
Explanation:
Work Study = Method Study + Work Measurement. Method Study: systematic recording and critical examination of existing and proposed ways of doing work to develop easier and more effective methods. Work Measurement: application of techniques to establish the time for a qualified worker to carry out a specified job at a defined level of performance.
Difficulty: basic Type: conceptual
Question 9 of 119
Original Exam: GATE (2016)
The correct sequence of steps in method study is:
✓ Correct Answer: A
Explanation:
The six steps of Method Study (SREDIM): (1) SELECT the work to be studied; (2) RECORD all relevant facts using charts and diagrams; (3) EXAMINE the recorded facts critically; (4) DEVELOP the most practical, economic, and effective method; (5) INSTALL the new method as standard practice; (6) MAINTAIN the new method and check results.
Difficulty: basic Type: conceptual
Question 10 of 119
Original Exam: IES (2015)
An operation process chart uses which symbols?
✓ Correct Answer: B
Explanation:
An Operation Process Chart (OPC) uses only TWO symbols: Circle (O) for Operation and Square for Inspection. OPC shows the sequence of all operations and inspections. It does NOT show transport, delay, or storage. A Flow Process Chart uses all five symbols: Operation, Inspection, Transport, Delay, and Storage.
Difficulty: basic Type: conceptual
Question 11 of 119
Original Exam: GATE (2013)
A flow process chart records activities using how many symbols?
✓ Correct Answer: C
Explanation:
A Flow Process Chart uses FIVE symbols (ASME standard): O - Operation, Arrow - Transport, Square - Inspection, D - Delay, Triangle - Storage. These five symbols comprehensively capture all activities in a process. The chart can be of three types: Material type, Man type, and Equipment type.
Difficulty: basic Type: conceptual
Question 12 of 119
Original Exam: IES (2019)
Which chart is used to study the relationship between the activities of a worker and a machine?
✓ Correct Answer: D
Explanation:
A Man-Machine Chart (Multiple Activity Chart) is used to study the relationship between worker and machine activities. It shows when the worker is working or idle, when the machine is running or idle, the cycle time, and opportunities for reducing idle time. It helps identify machine coupling opportunities.
Difficulty: basic Type: conceptual
Question 13 of 119
Original Exam: GATE (2020)
The critical examination technique in method study uses which questioning approach?
✓ Correct Answer: A
Explanation:
Critical Examination in Method Study uses the 5W1H questioning technique: PRIMARY questions: WHAT is done? WHY is it done? WHERE is it done? WHEN is it done? WHO does it? HOW is it done? SECONDARY questions: What ELSE could be done? What SHOULD be done? This systematic questioning challenges every aspect of the current method.
Difficulty: basic Type: conceptual
Question 14 of 119
Original Exam: GATE (2015)
Therbligs are used in:
✓ Correct Answer: B
Explanation:
Therbligs are the fundamental hand motions identified by Frank and Lillian Gilbreth for micro-motion study. 'Therblig' is 'Gilbreth' spelled backwards. There are 18 therbligs including Search, Find, Select, Grasp, Hold, Transport Loaded, Position, Assemble, Use, Disassemble, Inspect, Pre-position, Release Load, Transport Empty, Rest, Unavoidable Delay, Avoidable Delay, Plan.
Difficulty: intermediate Type: conceptual
Question 15 of 119
Original Exam: GATE (2016)
In time study, the observed time is converted to normal time by:
✓ Correct Answer: C
Explanation:
Normal Time = Observed Time x Performance Rating Factor. For example, if observed time = 5 minutes and performance rating = 110%, then Normal Time = 5 x 1.10 = 5.5 minutes. Normal time represents the time a worker performing at 100% (normal) pace would take. Standard Time = Normal Time + Allowances.
Difficulty: basic Type: conceptual
Question 16 of 119
Original Exam: IES (2014)
Standard time is calculated as:
✓ Correct Answer: D
Explanation:
Standard Time = Normal Time + Allowances = Normal Time x (1 + Allowance fraction). Where Normal Time = Observed Time x Performance Rating. Allowances include Personal allowances (5% typically), Fatigue allowances, and Delay allowances. Standard time is used for production planning, incentive wage calculation, cost estimation, and performance evaluation.
Difficulty: basic Type: conceptual
Question 17 of 119
Original Exam: GATE (2018)
An operator takes 8 minutes to complete a task. Performance rating is 120% and allowances are 15%. The standard time is:
✓ Correct Answer: A
Explanation:
Step 1: Normal Time = Observed Time x Performance Rating = 8 x 1.20 = 9.6 minutes. Step 2: Standard Time = Normal Time x (1 + Allowance fraction) = 9.6 x 1.15 = 11.04 minutes. The performance rating of 120% means the worker is 20% faster than normal, so normal time is higher than observed time.
Difficulty: intermediate Type: numerical
Question 18 of 119
Original Exam: GATE (2014)
The Westinghouse system of performance rating considers which factors?
✓ Correct Answer: B
Explanation:
The Westinghouse System evaluates four factors: (1) SKILL: proficiency in following a given method; (2) EFFORT: will to work, speed of work; (3) CONDITIONS: conditions affecting the operator (temperature, lighting, noise); (4) CONSISTENCY: variation in operator's times. The algebraic sum of all four factors is added to 1.00 to get the performance rating factor.
Difficulty: intermediate Type: conceptual
Question 19 of 119
Original Exam: IES (2016)
Allowances in time study are added to account for:
✓ Correct Answer: C
Explanation:
Allowances in time study: (1) Personal Allowance: time for personal needs (toilet, drinking water) - typically 5% of normal time; (2) Fatigue Allowance: time to recover from physical and mental fatigue; (3) Delay Allowance: unavoidable delays (machine adjustments, material waiting). Total allowance is typically 10-20% of normal time.
Difficulty: basic Type: conceptual
Question 20 of 119
Original Exam: GATE (2017)
If normal time for a job is 20 minutes and total allowances are 25%, the standard time is:
✓ Correct Answer: D
Explanation:
Standard Time = Normal Time x (1 + Allowance fraction) = 20 x (1 + 0.25) = 20 x 1.25 = 25 minutes. Alternatively: Allowance time = 25% of 20 = 5 minutes. Standard Time = 20 + 5 = 25 minutes.
Difficulty: basic Type: numerical
Question 21 of 119
Original Exam: GATE (2019)
In time study, 10 preliminary observations gave mean = 12 min and SD = 2 min. For 95% confidence and 5% accuracy, required observations are approximately:
✓ Correct Answer: A
Explanation:
n = (Z x s / (e x x_bar))^2 = (1.96 x 2 / (0.05 x 12))^2 = (3.92 / 0.60)^2 = (6.533)^2 = 42.68 approximately 43 observations. Z = 1.96 for 95% confidence, s = 2 min, e = 0.05, x_bar = 12 min.
Difficulty: intermediate Type: numerical
Question 22 of 119
Original Exam: GATE (2016)
Work sampling is also known as:
✓ Correct Answer: B
Explanation:
Work Sampling (Activity Sampling or Ratio Delay Study) is a technique for determining the proportion of time spent by workers or machines in various activities. It involves making a large number of instantaneous observations at random intervals. Developed by L.H.C. Tippett in 1934.
Difficulty: basic Type: conceptual
Question 23 of 119
Original Exam: IES (2017)
In work sampling, the required number of observations is given by:
✓ Correct Answer: C
Explanation:
In work sampling: n = Z^2 x p(1-p) / e^2. Where Z = confidence level factor (1.96 for 95%), p = estimated proportion of time in the activity, e = acceptable absolute error. For maximum sample size (p unknown), use p = 0.5 which gives maximum variance p(1-p) = 0.25.
Difficulty: intermediate Type: numerical
Question 24 of 119
Original Exam: GATE (2018)
In a work sampling study, a machine was found idle in 30 out of 200 observations. The percentage idle time is:
✓ Correct Answer: D
Explanation:
Percentage idle time = (Number of idle observations / Total observations) x 100 = (30/200) x 100 = 15%. The machine was working for 170 observations. Percentage working time = (170/200) x 100 = 85%. This information can be used to improve machine utilization and determine delay allowances.
Difficulty: basic Type: numerical
Question 25 of 119
Original Exam: IES (2019)
For work sampling with 95% confidence, 5% absolute error, and p = 0.4, required observations are approximately:
✓ Correct Answer: A
Explanation:
n = Z^2 x p(1-p) / e^2 = (1.96)^2 x 0.4 x 0.6 / (0.05)^2 = 3.8416 x 0.24 / 0.0025 = 0.9220 / 0.0025 = 368.64 approximately 369 observations. For p = 0.5 (maximum): n = 3.8416 x 0.25 / 0.0025 = 384.
Difficulty: intermediate Type: numerical
Question 26 of 119
Original Exam: GATE (2017)
MTM (Methods-Time Measurement) is a type of:
✓ Correct Answer: B
Explanation:
MTM (Methods-Time Measurement) is a Predetermined Motion Time System (PMTS) developed by Maynard, Stegemerten, and Schwab in 1948. PMTS establishes standard times for basic human motions based on extensive research. Other PMTS include MOST, MODAPTS, Work Factor, and Basic Motion Timestudy (BMT).
Difficulty: basic Type: conceptual
Question 27 of 119
Original Exam: IES (2018)
The time unit used in MTM is:
✓ Correct Answer: C
Explanation:
MTM uses TMU (Time Measurement Unit). 1 TMU = 0.00001 hours = 0.0006 minutes = 0.036 seconds. Therefore: 1 hour = 100,000 TMU; 1 minute = 1,667 TMU; 1 second = 27.8 TMU. TMU is a convenient unit for expressing the very small times associated with basic human motions.
Difficulty: basic Type: conceptual
Question 28 of 119
Original Exam: GATE (2019)
Which of the following is NOT a basic motion in MTM?
✓ Correct Answer: D
Explanation:
MTM basic motions include: Reach (R), Move (M), Turn (T), Apply Pressure (AP), Grasp (G), Position (P), Release (RL), Disengage (D), Eye Travel (ET), Eye Focus (EF), Body/Leg/Foot Motions. 'Think' is NOT a basic motion in MTM because MTM deals with physical motions only. Mental activities are not included in standard MTM tables.
Difficulty: basic Type: conceptual
Question 29 of 119
Original Exam: IES (2014)
In the Halsey Premium Plan, the worker receives a bonus of:
✓ Correct Answer: A
Explanation:
Halsey Premium Plan (F.A. Halsey, 1891): Worker receives a bonus of 50% of the time saved. Earnings = (Time worked x Wage rate) + 50% x (Time saved x Wage rate). Time saved = Standard time - Actual time. The employer retains 50% of time saved as cost reduction.
Difficulty: basic Type: conceptual
Question 30 of 119
Original Exam: GATE (2016)
In the Rowan Premium Plan, the bonus is calculated as:
✓ Correct Answer: B
Explanation:
Rowan Premium Plan (James Rowan, 1898): Bonus = (Time saved / Standard time) x Time worked x Wage rate. Total Earnings = Time worked x Wage rate + Bonus. Key feature: As the worker works faster, the bonus rate decreases, preventing excessive speed. Maximum earnings occur when actual time = 50% of standard time.
Difficulty: intermediate Type: numerical
Question 31 of 119
Original Exam: IES (2017)
In the Taylor Differential Piece Rate system, a worker who achieves or exceeds standard output receives:
✓ Correct Answer: C
Explanation:
Taylor Differential Piece Rate System: Two different piece rates: (1) High piece rate (120% of normal): for workers who meet or exceed standard output; (2) Low piece rate (80% of normal): for workers who fail to meet standard output. This creates a strong incentive to meet the standard.
Difficulty: intermediate Type: conceptual
Question 32 of 119
Original Exam: GATE (2018)
The Gantt Task and Bonus Plan provides:
✓ Correct Answer: D
Explanation:
Gantt Task and Bonus Plan (H.L. Gantt): (1) Below standard output: worker receives guaranteed day wage; (2) At standard output: worker receives day wage + 20% bonus; (3) Above standard output: worker receives high piece rate (120-130% of normal). This plan protects workers from loss due to poor standards and provides strong incentive.
Difficulty: intermediate Type: conceptual
Question 33 of 119
Original Exam: IES (2019)
A worker completes a job in 8 hours against standard time of 10 hours. Wage rate is Rs. 50/hour. Under Halsey 50% plan, earnings are:
✓ Correct Answer: A
Explanation:
Halsey 50% Plan: Earnings = (Actual time x Wage rate) + 50% x (Time saved x Wage rate). Time saved = 10 - 8 = 2 hours. Earnings = (8 x 50) + 0.5 x (2 x 50) = 400 + 50 = Rs. 450.
Difficulty: intermediate Type: numerical
Question 34 of 119
Original Exam: IES (2015)
Job evaluation is used to:
✓ Correct Answer: B
Explanation:
Job Evaluation is a systematic process for determining the relative worth of jobs within an organization to establish a rational and equitable wage structure. It evaluates the JOB (not the person) based on factors like skill required, effort required, responsibility, and working conditions.
Difficulty: basic Type: conceptual
Question 35 of 119
Original Exam: GATE (2016)
Merit rating (performance appraisal) is used to:
✓ Correct Answer: C
Explanation:
Merit Rating (Performance Appraisal) evaluates the PERFORMANCE of individual workers (not the job). It is used for salary increases and promotions, identifying training needs, providing feedback to workers, making transfer and layoff decisions, and validating selection procedures.
Difficulty: basic Type: conceptual
Question 36 of 119
Original Exam: GATE (2019)
Ergonomics is defined as the study of:
✓ Correct Answer: D
Explanation:
Ergonomics (from Greek: ergon = work, nomos = laws) is the scientific study of the relationship between workers and their work environment. It aims to optimize human well-being (reduce fatigue, injury, and discomfort) and improve system performance (productivity, quality, safety). Also called Human Factors Engineering.
Difficulty: basic Type: conceptual
Question 37 of 119
Original Exam: IES (2016)
Value Analysis (VA) was developed by:
✓ Correct Answer: A
Explanation:
Value Analysis (VA) was developed by Lawrence D. Miles at General Electric in the late 1940s. It is a systematic approach to improving the value of a product or process by examining its functions and finding less costly ways to achieve those functions. Value = Function / Cost.
Difficulty: basic Type: conceptual
Question 38 of 119
Original Exam: GATE (2018)
In Value Analysis, 'value' is defined as:
✓ Correct Answer: B
Explanation:
In Value Analysis: Value = Function / Cost. To improve value: increase function while keeping cost constant, decrease cost while keeping function constant, or increase function while decreasing cost. Types of value: Use value, Esteem value, Exchange value, and Cost value.
Difficulty: basic Type: conceptual
Question 39 of 119
Original Exam: GATE (2014)
The standard time for a job is 0.5 hours. If a worker works 8 hours per day, the standard output per day is:
✓ Correct Answer: C
Explanation:
Standard output per day = Available time / Standard time per unit = 8 hours / 0.5 hours per unit = 16 units per day. This is the expected output if the worker performs at 100% efficiency. Standard output is used for production planning, capacity calculation, and performance evaluation.
Difficulty: basic Type: numerical
Question 40 of 119
Original Exam: IES (2016)
If the standard time for a job is 15 minutes and the worker's efficiency is 80%, the actual time taken is:
✓ Correct Answer: D
Explanation:
Efficiency = Standard time / Actual time. Therefore: Actual time = Standard time / Efficiency = 15 / 0.80 = 18.75 minutes. The worker is performing at 80% efficiency, meaning they are slower than the standard pace.
Difficulty: basic Type: numerical
Question 41 of 119
Original Exam: IES (2014)
A time study shows observed times: 10, 12, 11, 13, 9 minutes. The mean observed time is:
✓ Correct Answer: A
Explanation:
Mean observed time = Sum / Number = (10 + 12 + 11 + 13 + 9) / 5 = 55 / 5 = 11 minutes. The mean is used as the representative observed time. Before calculating the mean, outliers (foreign elements) should be identified and removed.
Difficulty: basic Type: numerical
Question 42 of 119
Original Exam: GATE (2016)
The 'normal pace' in time study refers to:
✓ Correct Answer: B
Explanation:
Normal Pace (100% performance) is defined as the pace at which an average qualified worker can work without undue fatigue over a full working shift, day after day. It is the benchmark against which actual worker performance is compared during performance rating.
Difficulty: basic Type: conceptual
Question 43 of 119
Original Exam: GATE (2020)
In a time study, observed time = 0.5 min, performance rating = 90%, allowances = 10%. The standard time is:
✓ Correct Answer: C
Explanation:
Normal Time = 0.5 x 0.90 = 0.45 minutes. Standard Time = 0.45 x (1 + 0.10) = 0.45 x 1.10 = 0.495 minutes. The performance rating of 90% means the worker is slower than normal, so normal time is less than observed time.
Difficulty: intermediate Type: numerical
Question 44 of 119
Original Exam: IES (2019)
The correct formula for standard time when allowances are expressed as a percentage of standard time is:
✓ Correct Answer: D
Explanation:
When allowances (A) are expressed as % of STANDARD TIME: ST = NT / (1 - A). Derivation: ST = NT + A x ST. ST(1 - A) = NT. ST = NT / (1 - A). Example: NT = 20 min, A = 20% of ST. ST = 20 / 0.80 = 25 minutes. When allowances are % of NORMAL TIME: ST = NT x (1 + A).
Difficulty: intermediate Type: numerical
Question 45 of 119
Original Exam: GATE (2015)
The purpose of a SIMO chart is to:
✓ Correct Answer: A
Explanation:
SIMO Chart (Simultaneous Motion Chart): A graphical representation of the simultaneous activities of both hands of a worker, recorded at the therblig level. Used in micro-motion study. Features: time scale on vertical axis, left hand activities on left side, right hand activities on right side. Used for highly repetitive, short-cycle operations.
Difficulty: intermediate Type: conceptual
Question 46 of 119
Original Exam: GATE (2018)
The number of machines that can be assigned to one worker is determined by:
✓ Correct Answer: B
Explanation:
Number of machines per worker: n = (Machine running time + Loading/unloading time) / (Loading/unloading time + Walking time between machines). This formula ensures the worker can service all machines without any machine waiting.
Difficulty: intermediate Type: numerical
Question 47 of 119
Original Exam: GATE (2017)
A worker takes 2 min to load/unload a machine. Machine runs automatically for 8 min. Walking time is 0.5 min. Maximum machines the worker can handle:
✓ Correct Answer: C
Explanation:
n = (Machine running time + Loading time) / (Loading time + Walking time) = (8 + 2) / (2 + 0.5) = 10 / 2.5 = 4 machines. Verification: Worker time per cycle = 4 x 2.5 = 10 minutes = Machine cycle time. No idle time for either worker or machines.
Difficulty: intermediate Type: numerical
Question 48 of 119
Original Exam: IES (2015)
Which of the following is NOT a technique of work measurement?
✓ Correct Answer: D
Explanation:
Techniques of Work Measurement: Time Study, Work Sampling, Predetermined Motion Time Systems (PMTS), Standard Data Method, Analytical Estimating, and Comparative Estimating. PERT and CPM are project scheduling techniques, NOT work measurement techniques. They are used for planning and scheduling projects.
Difficulty: basic Type: conceptual
Question 49 of 119
Original Exam: IES (2016)
The 'rating factor' in time study is expressed as a percentage where 100% represents:
✓ Correct Answer: A
Explanation:
In time study, the rating factor (performance rating) is expressed as a percentage where 100% represents NORMAL worker performance. Rating > 100%: worker is faster than normal. Rating < 100%: worker is slower than normal. Normal Time = Observed Time x (Rating / 100).
Difficulty: basic Type: conceptual
Question 50 of 119
Original Exam: GATE (2013)
In a time study, observed time = 10 min and performance rating = 80%. The normal time is:
✓ Correct Answer: B
Explanation:
Normal Time = Observed Time x Performance Rating = 10 x (80/100) = 10 x 0.80 = 8 minutes. The worker is performing at 80% of normal pace (slower than normal). The normal time (8 minutes) is less than the observed time (10 minutes).
Difficulty: basic Type: numerical
Question 51 of 119
Original Exam: GATE (2019)
The 'personal allowance' in time study is typically:
✓ Correct Answer: C
Explanation:
Personal Allowance is provided for personal needs such as toilet visits, drinking water, washing hands. Standard personal allowance is typically 5% of normal time (approximately 24 minutes in an 8-hour shift). ILO recommends 5% as a standard personal allowance. Fatigue allowance varies with job conditions. Delay allowance is determined by work sampling.
Difficulty: basic Type: conceptual
Question 52 of 119
Original Exam: GATE (2014)
The 'cycle time' in a repetitive operation is:
✓ Correct Answer: D
Explanation:
Cycle Time is the time for one complete cycle of a repetitive operation, from the start of one unit to the start of the next unit. It includes all operation elements, machine time, and any waiting time within the cycle. Cycle time is the basis for calculating standard time, determining production rate, and line balancing.
Difficulty: basic Type: conceptual
Question 53 of 119
Original Exam: IES (2021)
Takt time is defined as:
✓ Correct Answer: A
Explanation:
Takt Time = Available Production Time / Customer Demand Rate. 'Takt' is German for 'beat'. Example: Available time = 480 min/day, Customer demand = 240 units/day. Takt time = 480/240 = 2 min/unit. Used in lean manufacturing for production pacing and assembly line balancing.
Difficulty: intermediate Type: conceptual
Question 54 of 119
Original Exam: IES (2018)
The 'utilization' of a machine is defined as:
✓ Correct Answer: B
Explanation:
Machine Utilization = (Actual hours worked / Available hours) x 100%. It measures the fraction of available time that the machine is actually being used. Utilization is different from efficiency: Efficiency = Standard hours produced / Actual hours worked. OEE = Availability x Performance x Quality.
Difficulty: basic Type: conceptual
Question 55 of 119
Original Exam: GATE (2016)
The 'Economic Order Quantity' (EOQ) formula is:
✓ Correct Answer: C
Explanation:
EOQ = sqrt(2DS/H). Where D = Annual demand, S = Ordering cost per order, H = Holding cost per unit per year. At EOQ: Ordering cost = Holding cost. EOQ minimizes total inventory cost. Assumptions: constant demand, constant lead time, no stockouts, no quantity discounts, instantaneous replenishment.
Difficulty: intermediate Type: numerical
Question 56 of 119
Original Exam: GATE (2018)
Annual demand = 1000 units, ordering cost = Rs. 50/order, holding cost = Rs. 2/unit/year. The EOQ is:
✓ Correct Answer: D
Explanation:
EOQ = sqrt(2DS/H) = sqrt(2 x 1000 x 50 / 2) = sqrt(50000) = 223.6 approximately 224 units. Number of orders per year = 1000/224 = 4.46. Total annual cost = (1000/224)x50 + (224/2)x2 = 223.2 + 224 = Rs. 447.2.
Difficulty: intermediate Type: numerical
Question 57 of 119
Original Exam: IES (2019)
The 'reorder point' (ROP) in inventory management is calculated as:
✓ Correct Answer: A
Explanation:
Reorder Point (ROP) = Average demand during lead time + Safety stock = (d x L) + SS. Where d = average daily demand, L = lead time in days, SS = safety stock. Example: d = 10 units/day, L = 5 days, SS = 20 units. ROP = (10 x 5) + 20 = 70 units.
Difficulty: intermediate Type: numerical
Question 58 of 119
Original Exam: GATE (2017)
The 'critical path' in a project network is the path that:
✓ Correct Answer: B
Explanation:
Critical Path: The longest path through the project network that determines the minimum project duration. Characteristics: zero total float (any delay on the critical path delays the entire project). Total Float = Latest Start Time - Earliest Start Time. Non-critical activities have positive total float.
Difficulty: intermediate Type: conceptual
Question 59 of 119
Original Exam: IES (2016)
In PERT, the expected time for an activity is calculated as:
✓ Correct Answer: C
Explanation:
PERT Expected Time: te = (a + 4m + b) / 6. Where a = optimistic time, m = most likely time, b = pessimistic time. Variance: sigma^2 = ((b - a) / 6)^2. PERT is used for projects with uncertain activity durations. CPM uses deterministic (single) time estimates.
Difficulty: intermediate Type: numerical
Question 60 of 119
Original Exam: IES (2020)
The 'line balancing' problem in assembly line design aims to:
✓ Correct Answer: D
Explanation:
Line Balancing: Assigning tasks to workstations such that precedence constraints are satisfied, cycle time constraint is met, and idle time is minimized. Line efficiency = (Sum of task times) / (Number of workstations x Cycle time) x 100%. Minimum workstations = ceil(Sum of task times / Cycle time).
Difficulty: intermediate Type: conceptual
Question 61 of 119
Original Exam: GATE (2019)
The 'Pareto principle' (80-20 rule) in productivity improvement states that:
✓ Correct Answer: A
Explanation:
Pareto Principle (80-20 Rule): 80% of effects come from 20% of causes. In productivity improvement: 80% of quality problems are caused by 20% of defect types; 80% of inventory value is in 20% of items (ABC analysis). Focus improvement efforts on the vital few (20%) causes that produce the majority (80%) of problems.
Difficulty: basic Type: conceptual
Question 62 of 119
Original Exam: IES (2018)
The 'fishbone diagram' (Ishikawa diagram) is used to:
✓ Correct Answer: B
Explanation:
Fishbone Diagram (Cause-and-Effect Diagram, Ishikawa Diagram): A graphical tool for identifying and organizing potential causes of a problem. Common cause categories (6M): Man, Machine, Method, Material, Measurement, Mother Nature (environment). Part of the 7 basic quality tools.
Difficulty: basic Type: conceptual
Question 63 of 119
Original Exam: IES (2017)
The 'ABC analysis' in inventory management classifies items based on:
✓ Correct Answer: C
Explanation:
ABC Analysis: Classifies inventory items based on annual consumption value. Class A: 10-20% of items, 70-80% of annual value - tight control. Class B: 30% of items, 15-25% of annual value - moderate control. Class C: 50-60% of items, 5-10% of annual value - simple control. Based on the Pareto principle.
Difficulty: basic Type: conceptual
Question 64 of 119
Original Exam: GATE (2013)
The 'time and motion study' was pioneered by:
✓ Correct Answer: D
Explanation:
Time and Motion Study was pioneered by: (1) F.W. Taylor (1856-1915): developed time study and scientific management principles; (2) Frank Gilbreth (1868-1924) and Lillian Gilbreth: developed motion study, micro-motion study, therbligs, and principles of motion economy.
Difficulty: basic Type: conceptual
Question 65 of 119
Original Exam: IES (2015)
The 'scientific management' principles of F.W. Taylor include:
✓ Correct Answer: A
Explanation:
Taylor's Principles of Scientific Management (1911): (1) Science, not rule of thumb: replace rule-of-thumb methods with scientifically determined best methods; (2) Scientific selection and training; (3) Cooperation between management and workers; (4) Equal division of work and responsibility.
Difficulty: basic Type: conceptual
Question 66 of 119
Original Exam: GATE (2020)
The 'Hawthorne effect' in productivity studies refers to:
✓ Correct Answer: B
Explanation:
Hawthorne Effect: The tendency of people to modify their behavior when they know they are being observed. Named after the Hawthorne Works studies by Elton Mayo (1924-1932). Implication for work study: time study results may be biased if workers perform differently when being timed.
Difficulty: intermediate Type: conceptual
Question 67 of 119
Original Exam: GATE (2014)
The 'functional foremanship' concept was introduced by:
✓ Correct Answer: C
Explanation:
Functional Foremanship was introduced by F.W. Taylor. He proposed replacing the single foreman with EIGHT specialized foremen: Route clerk, Instruction card clerk, Time and cost clerk, Shop disciplinarian, Gang boss, Speed boss, Repair boss, and Inspector. The idea was that no single person could be expert in all aspects of supervision.
Difficulty: basic Type: conceptual
Question 68 of 119
Original Exam: IES (2014)
The 'Gantt chart' was developed by Henry Gantt primarily for:
✓ Correct Answer: D
Explanation:
Gantt Chart (Henry Gantt, 1910-1915): A bar chart for production scheduling and progress monitoring. Features: activities on vertical axis, time scale on horizontal axis, horizontal bars showing duration and schedule. Limitations: does not show dependencies between activities, difficult to update for complex projects.
Difficulty: basic Type: conceptual
Question 69 of 119
Original Exam: GATE (2019)
The 'value engineering' job plan consists of which phases?
✓ Correct Answer: A
Explanation:
Value Engineering Job Plan (Lawrence Miles): (1) INFORMATION phase: gather all relevant information; (2) FUNCTION ANALYSIS phase: identify and analyze functions using FAST diagram; (3) CREATIVE phase: brainstorm alternatives; (4) EVALUATION phase: evaluate alternatives; (5) DEVELOPMENT phase: develop best alternatives; (6) PRESENTATION phase: present recommendations.
Difficulty: intermediate Type: conceptual
Question 70 of 119
Original Exam: IES (2022)
The 'productivity' of a system can be improved by:
✓ Correct Answer: B
Explanation:
Productivity = Output / Input. Productivity can be improved by: (1) Increasing output while keeping inputs constant; (2) Decreasing inputs while keeping output constant; (3) Increasing output more than the increase in inputs; (4) Decreasing inputs more than the decrease in output. All scenarios result in a higher Output/Input ratio.
Difficulty: basic Type: conceptual
Question 71 of 119
Original Exam: GATE (2017)
The 'Merrick Differential Piece Rate' system uses how many piece rates?
✓ Correct Answer: C
Explanation:
Merrick Differential Piece Rate System (D.C. Merrick): Uses THREE piece rates: (1) Low piece rate (83% of standard rate): for workers producing less than 83% of standard output; (2) Medium piece rate (100% of standard rate): for workers producing 83-100% of standard output; (3) High piece rate (120% of standard rate): for workers producing more than 100% of standard output.
Difficulty: intermediate Type: conceptual
Question 72 of 119
Original Exam: IES (2019)
The 'Scanlon Plan' is a type of:
✓ Correct Answer: D
Explanation:
Scanlon Plan (Joseph Scanlon, 1930s): A group incentive plan based on labour cost savings. Bonus pool = Savings in labour costs compared to a historical ratio of labour costs to sales value. Bonus shared among all employees. Promotes teamwork, employee involvement, and continuous improvement.
Difficulty: intermediate Type: conceptual
Question 73 of 119
Original Exam: GATE (2017)
The 'Bedaux Point System' uses a unit called 'B' where 1 B represents:
✓ Correct Answer: A
Explanation:
Bedaux Point System (Charles Bedaux, 1916): Uses 'B' (Bedaux unit). 1 B = 1 minute of work at normal pace (including allowances). Standard output = 60 B per hour. Worker's efficiency = (B points earned / 60) x 100%. Bonus for B points earned above 60 per hour.
Difficulty: intermediate Type: conceptual
Question 74 of 119
Original Exam: GATE (2015)
The 'Emerson Efficiency Plan' provides bonus only when efficiency exceeds:
✓ Correct Answer: B
Explanation:
Emerson Efficiency Plan (H. Emerson): Bonus starts when efficiency exceeds 66.67% (two-thirds of standard). Below 66.67%: worker receives only day wage. Between 66.67% and 100%: graduated bonus. At 100% efficiency: bonus = 20% of day wage. Above 100%: bonus increases proportionally.
Difficulty: intermediate Type: conceptual
Question 75 of 119
Original Exam: IES (2016)
The 'learning curve' shows that:
✓ Correct Answer: C
Explanation:
Learning Curve (Experience Curve): As cumulative production doubles, the time per unit decreases by a constant percentage. For an 80% learning curve: when cumulative production doubles, time per unit becomes 80% of the previous time. Formula: T_n = T_1 x n^b, where b = log(learning rate)/log(2).
Difficulty: intermediate Type: conceptual
Question 76 of 119
Original Exam: GATE (2020)
If the first unit takes 100 hours and the learning curve is 80%, how many hours will the 4th unit take?
✓ Correct Answer: D
Explanation:
For an 80% learning curve: 1st unit: 100 hours. 2nd unit (1st doubling): 100 x 0.80 = 80 hours. 4th unit (2nd doubling): 80 x 0.80 = 64 hours. 8th unit (3rd doubling): 64 x 0.80 = 51.2 hours. The 4th unit takes 64 hours.
Difficulty: intermediate Type: numerical
Question 77 of 119
Original Exam: IES (2020)
The 'process capability index' Cp is defined as:
✓ Correct Answer: A
Explanation:
Process Capability Index Cp = (USL - LSL) / 6sigma. Where USL = Upper Specification Limit, LSL = Lower Specification Limit, sigma = process standard deviation. Cp = 1: process spread equals specification width. Cp > 1: process is capable. Cp < 1: process is not capable. For Six Sigma quality: Cp = 2.
Difficulty: intermediate Type: numerical
Question 78 of 119
Original Exam: GATE (2020)
The 'control chart' in statistical quality control is used to:
✓ Correct Answer: B
Explanation:
Control Chart (Shewhart Chart, 1924): Components: Center line (CL), Upper Control Limit (UCL = CL + 3sigma), Lower Control Limit (LCL = CL - 3sigma). Purpose: distinguish between Common Cause variation (inherent, random) and Special Cause variation (assignable, non-random). Types: X-bar and R chart, p-chart, c-chart.
Difficulty: intermediate Type: numerical
Question 79 of 119
Original Exam: IES (2016)
The 'string diagram' is used to:
✓ Correct Answer: C
Explanation:
A String Diagram is a scale plan of the workplace on which a thread is used to trace and measure the path of a worker, material, or equipment. Used to: show actual path of movement, measure total distance traveled, identify unnecessary movements, compare alternative layouts, and improve workplace layout.
Difficulty: basic Type: conceptual
Question 80 of 119
Original Exam: GATE (2016)
The 'two-handed process chart' is used to:
✓ Correct Answer: D
Explanation:
Two-Handed Process Chart (Left-Hand Right-Hand Chart): Records the activities of BOTH HANDS of a single worker simultaneously on a time scale. Uses the same five symbols as a flow process chart applied to each hand separately. Particularly useful for assembly operations, packaging, and other manual operations.
Difficulty: basic Type: conceptual
Question 81 of 119
Original Exam: IES (2017)
The 'travel chart' (from-to chart) in plant layout is used to:
✓ Correct Answer: A
Explanation:
Travel Chart (From-To Chart): A matrix showing the volume (or frequency) of material flow between all pairs of departments or workstations. Used for evaluating alternative plant layouts, identifying high-traffic flows, calculating total material handling cost, and systematic layout planning (SLP).
Difficulty: intermediate Type: conceptual
Question 82 of 119
Original Exam: GATE (2019)
The 'predetermined time' for a 'reach' motion in MTM depends on:
✓ Correct Answer: B
Explanation:
In MTM, the time for a REACH (R) motion depends on: (1) Distance of reach; (2) Type of reach: Case A (fixed location), Case B (single object, variable location), Case C (jumbled objects), Case D (very small object), Case E (indefinite location). MTM tables give times in TMU for each combination.
Difficulty: intermediate Type: numerical
Question 83 of 119
Original Exam: GATE (2019)
The 'MOST' system is faster to apply than MTM-1 by a factor of approximately:
✓ Correct Answer: C
Explanation:
MOST (Maynard Operation Sequence Technique) is approximately 40-50 times faster to apply than MTM-1. MOST uses three sequence models: (1) General Move: A-B-G-A-B-P-A; (2) Controlled Move: A-B-G-M-X-I-A; (3) Tool Use sequence. Each parameter is assigned an index value (0, 1, 3, 6, 10, 16). Total time = Sum of index values x 10 TMU.
Difficulty: intermediate Type: conceptual
Question 84 of 119
Original Exam: IES (2018)
The 'job enrichment' concept in work design refers to:
✓ Correct Answer: D
Explanation:
Job Enrichment (Frederick Herzberg): Adding more challenging, meaningful, and responsible tasks to a job (vertical loading). Increases task variety, task identity, task significance, autonomy, and feedback. Job Enrichment vs. Job Enlargement: Enlargement = horizontal loading (more tasks of same level); Enrichment = vertical loading (higher-level tasks).
Difficulty: intermediate Type: conceptual
Question 85 of 119
Original Exam: GATE (2014)
The 'Gilbreth's classification of motions' divides motions into how many classes based on body parts used?
✓ Correct Answer: A
Explanation:
Gilbreth's Classification of Motions: Class 1: Finger motions only; Class 2: Finger and wrist motions; Class 3: Finger, wrist, and forearm motions; Class 4: Finger, wrist, forearm, and upper arm motions; Class 5: Finger, wrist, forearm, upper arm, and shoulder motions. Lower class motions are faster and less fatiguing.
Difficulty: intermediate Type: conceptual
Question 86 of 119
Original Exam: GATE (2016)
The 'Westinghouse system' performance rating adds the sum of factor ratings to:
✓ Correct Answer: B
Explanation:
Westinghouse System: The algebraic sum of all four factor ratings (Skill + Effort + Conditions + Consistency) is added to 1.00 to get the performance rating factor. Example: Sum = +0.14. Performance Rating = 1.00 + 0.14 = 1.14 (114%). Normal Time = Observed Time x 1.14.
Difficulty: intermediate Type: numerical
Question 87 of 119
Original Exam: IES (2022)
The 'delay allowance' in time study is determined by:
✓ Correct Answer: C
Explanation:
Delay Allowance (Unavoidable Delay Allowance) is determined by conducting a WORK SAMPLING study over a representative period (typically several days or weeks). The work sampling study records the frequency of unavoidable delays and calculates the percentage of time spent in delays. This percentage becomes the delay allowance.
Difficulty: intermediate Type: numerical
Question 88 of 119
Original Exam: IES (2017)
The 'standard data' for a drilling operation would typically include time as a function of:
✓ Correct Answer: D
Explanation:
Standard Data for machining operations (like drilling) is expressed as a function of relevant numerical parameters: (1) Hole diameter: larger diameter = more time; (2) Hole depth: deeper hole = more time; (3) Material: harder material = slower cutting speed = more time; (4) Surface finish required. Standard data tables or regression equations relate these parameters to machining time.
Difficulty: intermediate Type: numerical
Question 89 of 119
Original Exam: GATE (2016)
The 'MTM system' was developed in:
✓ Correct Answer: A
Explanation:
MTM (Methods-Time Measurement) was developed in 1948 by H.B. Maynard, G.J. Stegemerten, and J.L. Schwab at the Westinghouse Electric Corporation. Key milestones: 1948: MTM-1 published; 1965: MTM-2 (simplified); 1970: MTM-3 (further simplified); 1985: MOST developed by Kjell Zandin.
Difficulty: basic Type: conceptual
Question 90 of 119
Original Exam: IES (2019)
The 'work factor' system is a type of:
✓ Correct Answer: B
Explanation:
Work Factor System: A Predetermined Motion Time System (PMTS) developed by J.H. Quick, W.J. Shea, and R.E. Koehler at RCA in the 1930s. Uses 'work factors' to account for difficulty of motion (weight, precision, change of direction, care). Basic time unit: 0.0001 minute.
Difficulty: intermediate Type: conceptual
Question 91 of 119
Original Exam: GATE (2018)
The 'Rucker Plan' uses which ratio as the basis for bonus calculation?
✓ Correct Answer: C
Explanation:
Rucker Plan (Allen Rucker): Similar to Scanlon Plan but uses the ratio of labour cost to VALUE ADDED (not sales) as the basis for bonus calculation. Value Added = Sales - Cost of purchased materials and services. Advantage: Value added is not affected by changes in material costs, making the bonus more directly related to employee productivity.
Type: conceptual
Question 92 of 119
Original Exam: GATE (2017)
The 'Emerson efficiency bonus' plan provides maximum bonus when efficiency reaches:
✓ Correct Answer: D
Explanation:
Emerson Efficiency Plan: At 100% efficiency: bonus = 20% of day wage. Above 100%: bonus increases proportionally. The maximum practical bonus point is at 133.33% efficiency where the bonus equals the day wage (100% bonus). At 133.33% efficiency, total earnings = 2 x day wage.
Type: conceptual
Question 93 of 119
Original Exam: IES (2018)
The 'Rowan plan' provides maximum earnings when actual time equals what fraction of standard time?
✓ Correct Answer: A
Explanation:
Rowan Plan: Earnings = Actual time x Wage rate x (2 - Actual time / Standard time). To find maximum: dE/d(Actual time) = 0. Let t = actual time, S = standard time. E = tw(2S-t)/S. dE/dt = w(2S-2t)/S = 0. t = S/2. Maximum earnings occur when actual time = S/2 (half of standard time).
Type: numerical
Question 94 of 119
Original Exam: IES (2020)
The 'FAST diagram' in Value Analysis is used to:
✓ Correct Answer: B
Explanation:
FAST (Function Analysis System Technique) Diagram: A graphical tool to organize and display functions in a logical hierarchy. Answers: 'HOW is the function performed?' (moving right) and 'WHY is the function performed?' (moving left). Helps identify all functions, understand relationships, identify unnecessary functions, and focus cost reduction efforts.
Difficulty: intermediate Type: conceptual
Question 95 of 119
Original Exam: GATE (2017)
The 'indirect labour' in a manufacturing organization includes:
✓ Correct Answer: C
Explanation:
Direct Labour: workers who directly work on the product (machine operators, assemblers, welders). Indirect Labour: workers who support production but do not directly work on the product. Examples: maintenance workers, material handlers, supervisors, quality inspectors, tool room workers. Indirect labour costs are overhead costs.
Difficulty: basic Type: conceptual
Question 96 of 119
Original Exam: IES (2019)
The 'break-even point' in production is where:
✓ Correct Answer: D
Explanation:
Break-Even Point (BEP): Total Revenue = Total Cost (Fixed Cost + Variable Cost). At BEP, profit = 0. BEP (in units) = Fixed Cost / (Selling Price per unit - Variable Cost per unit) = Fixed Cost / Contribution per unit. Above BEP: profit zone. Below BEP: loss zone.
Difficulty: basic Type: conceptual
Question 97 of 119
Original Exam: GATE (2015)
The 'standard hour' concept is used to:
✓ Correct Answer: A
Explanation:
Standard Hour: A unit of measurement representing the amount of work that should be done in one hour at standard performance (100% efficiency). Used to: compare output of different jobs, calculate worker efficiency (Efficiency = Standard hours produced / Actual hours worked), calculate incentive wages, and measure departmental productivity.
Difficulty: basic Type: conceptual
Question 98 of 119
Original Exam: GATE (2013)
The 'snap-back timing' method in time study means:
✓ Correct Answer: B
Explanation:
Snap-Back (Reset) Method: The stopwatch is read at the end of each element and immediately snapped back (reset) to zero. The reading gives the time for that element directly. Advantages: easy to detect unusual elements, easy to calculate element times. Disadvantages: time is lost during snap-back, cumulative errors.
Difficulty: basic Type: conceptual
Question 99 of 119
Original Exam: IES (2018)
In time study, an element is considered 'foreign' if:
✓ Correct Answer: C
Explanation:
Foreign Elements in time study are activities that are NOT part of the regular job cycle. They occur irregularly and should NOT be included in the standard time calculation. Examples: machine breakdown, material shortage, receiving instructions from supervisor. When a foreign element occurs, the analyst notes it separately and excludes it from normal time calculation.
Difficulty: basic Type: conceptual
Question 100 of 119
Original Exam: IES (2018)
The 'principles of motion economy' are primarily concerned with:
✓ Correct Answer: D
Explanation:
Principles of Motion Economy (Frank Gilbreth, refined by Barnes) are grouped into three categories: (1) Use of Human Body: both hands should begin and end motions simultaneously, use lowest classification of body movement; (2) Arrangement of Workplace: fixed locations for tools and materials; (3) Design of Tools and Equipment: combine tools, use foot pedals.
Difficulty: intermediate Type: conceptual
Question 101 of 119
Original Exam: GATE (2018)
The 'motion economy' principle that states 'both hands should begin and end their motions simultaneously' is related to:
✓ Correct Answer: A
Explanation:
Principles of Motion Economy are grouped into three categories: (1) USE OF THE HUMAN BODY: both hands should begin and end motions simultaneously, both hands should not be idle at the same time, motions of arms should be in opposite and symmetrical directions; (2) ARRANGEMENT OF WORKPLACE; (3) DESIGN OF TOOLS AND EQUIPMENT.
Difficulty: intermediate Type: conceptual
Question 102 of 119
Original Exam: IES (2021)
The 'standard time' established by time study is valid for:
✓ Correct Answer: B
Explanation:
Standard Time is valid for: A QUALIFIED worker (trained, experienced) performing the job using the SPECIFIED METHOD under SPECIFIED CONDITIONS (normal working conditions). Key assumptions: worker is qualified and trained, specified method is followed, normal working conditions prevail, worker performs at 100% efficiency.
Difficulty: basic Type: conceptual
Question 103 of 119
Original Exam: IES (2016)
The 'work content' of a job is defined as:
✓ Correct Answer: C
Explanation:
Work Content: The total amount of work in a job measured in standard hours. It represents the time a qualified worker would take to complete the job at standard performance, including all allowances. Work content = Basic work content + Excess work content. Reducing excess work content is the goal of work study.
Difficulty: basic Type: conceptual
Question 104 of 119
Original Exam: GATE (2021)
The 'productivity measurement' at the national level uses which indicator?
✓ Correct Answer: D
Explanation:
National-level productivity is measured by: (1) Labour productivity = GDP / Total employment (GDP per worker) or GDP / Total hours worked (GDP per hour worked); (2) Total Factor Productivity (TFP) = GDP / (Weighted combination of all inputs). GDP per hour worked is the most internationally comparable measure.
Difficulty: intermediate Type: conceptual
Question 105 of 119
Original Exam: GATE (2019)
The 'capacity' of a machine in standard hours is calculated as:
✓ Correct Answer: A
Explanation:
Machine Capacity (in standard hours) = Available hours x Utilization x Efficiency. Where: Available hours = total hours the machine is available; Utilization = fraction of available time the machine is actually running; Efficiency = ratio of standard hours produced to actual hours run. This gives the effective capacity in standard hours.
Difficulty: intermediate Type: numerical
Question 106 of 119
Original Exam: IES (2016)
The 'in a time study, the 'select' step involves:
✓ Correct Answer: B
Explanation:
The SELECT step in Method Study/Time Study involves choosing which job or operation to study. Selection criteria: high cost operations, bottleneck operations, operations with high scrap or rework rates, operations with safety hazards, operations with worker complaints, new operations, and operations with high overtime.
Difficulty: basic Type: conceptual
Question 107 of 119
Original Exam: IES (2021)
The 'Delphi method' for productivity forecasting involves:
✓ Correct Answer: C
Explanation:
Delphi Method: A structured communication technique for forecasting and decision-making that relies on a panel of experts. Process: (1) Select experts; (2) Send questionnaire; (3) Summarize responses and send back anonymously; (4) Experts revise estimates; (5) Repeat until consensus. Eliminates group dynamics and encourages honest opinions.
Difficulty: intermediate Type: conceptual
Question 108 of 119
Original Exam: GATE (2015)
The 'float' (slack) of an activity in project management is:
✓ Correct Answer: D
Explanation:
Float (Slack) = the amount of time an activity can be delayed without delaying the project completion. Total Float = Latest Start Time - Earliest Start Time = Latest Finish Time - Earliest Finish Time. Free Float = Earliest Start Time of successor - Earliest Finish Time of activity. Critical activities have zero total float.
Difficulty: basic Type: conceptual
Question 109 of 119
Original Exam: GATE (2018)
The 'synthetic time' in work measurement is obtained from:
✓ Correct Answer: A
Explanation:
Synthetic Time (Synthesis): Time values obtained from predetermined motion time systems (PMTS like MTM, MOST) or from standard data tables compiled from previous time studies. Advantages: no stopwatch needed, can be established before the job starts, consistent standards, useful for new jobs, eliminates performance rating subjectivity.
Difficulty: intermediate Type: conceptual
Question 110 of 119
Original Exam: IES (2020)
The 'coefficient of variation' in time study is used to:
✓ Correct Answer: B
Explanation:
Coefficient of Variation (CV) = (Standard Deviation / Mean) x 100%. In time study, CV assesses the consistency of observed times. High CV indicates high variability, suggesting more observations may be needed or the job may not be well-defined. CV is also used to determine required number of observations: n = (Z x CV / e)^2.
Difficulty: intermediate Type: numerical
Question 111 of 119
Original Exam: GATE (2021)
The 'maximum acceptable weight' for manual lifting (for males) as per ergonomic guidelines is approximately:
✓ Correct Answer: C
Explanation:
According to ergonomic guidelines and international standards (ILO, NIOSH): Maximum acceptable weight for manual lifting for males: approximately 25 kg (55 lbs) under ideal conditions. For females: approximately 16 kg (35 lbs). The NIOSH Lifting Equation calculates the Recommended Weight Limit (RWL) based on horizontal distance, vertical height, frequency, and coupling.
Difficulty: basic Type: conceptual
Question 112 of 119
Original Exam: IES (2018)
The 'in the point rating method of job evaluation, which is typically NOT a compensable factor?
✓ Correct Answer: D
Explanation:
Point Rating Method of Job Evaluation uses compensable factors. The four main compensable factor groups (NEMA/NMTA system): (1) SKILL: education, experience, initiative; (2) EFFORT: physical demand, mental demand; (3) RESPONSIBILITY: for equipment, material, safety, work of others; (4) JOB CONDITIONS: working conditions, hazards. Worker's age is NOT a compensable factor as it would be discriminatory.
Difficulty: intermediate Type: conceptual
Question 113 of 119
Original Exam: GATE (2018)
The 'Gantt Task and Bonus Plan' provides a bonus of what percentage at standard output?
✓ Correct Answer: A
Explanation:
Gantt Task and Bonus Plan (H.L. Gantt): (1) Below standard output: worker receives guaranteed day wage only; (2) AT standard output: worker receives day wage + 20% BONUS; (3) Above standard output: worker receives high piece rate (120-130% of normal). The 20% bonus at standard output is a key feature of this plan.
Difficulty: intermediate Type: conceptual
Question 114 of 119
Original Exam: IES (2017)
The 'work sampling' technique was developed by:
✓ Correct Answer: B
Explanation:
Work Sampling (Activity Sampling or Ratio Delay Study) was developed by L.H.C. Tippett in 1934 at the British Cotton Industry Research Association. He applied statistical sampling theory to work measurement. The technique was later popularized by R.L. Morrow in the USA. It is based on the statistical principle that a random sample is representative of the population.
Difficulty: basic Type: conceptual
Question 115 of 119
Original Exam: IES (2020)
The 'elemental time study' method involves:
✓ Correct Answer: C
Explanation:
Elemental Time Study (Stop-Watch Time Study) involves: (1) Breaking the job into distinct elements; (2) Timing each element separately using a stopwatch; (3) Rating the worker's performance for each element; (4) Calculating normal time for each element; (5) Adding allowances to get standard time; (6) Summing element standard times to get total standard time.
Difficulty: basic Type: conceptual
Question 116 of 119
Original Exam: GATE (2022)
The 'productivity improvement' through automation is best measured by:
✓ Correct Answer: D
Explanation:
Productivity improvement through automation should be measured by the increase in output per unit of TOTAL input (multi-factor productivity), not just labour productivity. Automation increases capital input while reducing labour input. True productivity improvement = more output from the same total resources (labour + capital + materials + energy).
Difficulty: intermediate Type: conceptual
Question 117 of 119
Original Exam: GATE (2020)
The 'standard time' for a job is 30 minutes. A worker produces 20 units in an 8-hour shift. The worker's efficiency is:
✓ Correct Answer: A
Explanation:
Standard output in 8 hours = 480 min / 30 min per unit = 16 units. Actual output = 20 units. Efficiency = (Actual output / Standard output) x 100% = (20/16) x 100% = 125%. The worker produced more than the standard output, so efficiency exceeds 100%.
Difficulty: intermediate Type: numerical
Question 118 of 119
Original Exam: IES (2015)
The 'motion study' technique developed by Frank Gilbreth uses which recording tool for detailed analysis?
✓ Correct Answer: B
Explanation:
Frank Gilbreth's Micro-Motion Study uses: (1) High-speed camera: records worker's motions on film; (2) Microchronometer: a clock with a large face placed in the field of view of the camera, allowing time to be read from the film frames. The film is analyzed frame by frame to identify and time each therblig (basic motion).
Difficulty: intermediate Type: numerical
Question 119 of 119
Original Exam: GATE (2015)
The 'main advantage of work sampling over time study' is:
✓ Correct Answer: C
Explanation:
Advantages of Work Sampling over Time Study: (1) Multiple workers/machines can be studied simultaneously; (2) No stopwatch required; (3) Less disruptive - workers are less conscious of being observed; (4) Suitable for long-cycle, irregular, or non-repetitive jobs; (5) Less expensive for long studies; (6) Analyst can do other work between observations.
Difficulty: basic Type: conceptual